I just recieved my Journeyman CNC, I also recieved the QCW Frame and folding table. My question is the order to follow for assembly? I am thinking,
1 QCW Frame
2 Folding Table
3 Rails
Any thoughts?
Thanks
Brent
I just recieved my Journeyman CNC, I also recieved the QCW Frame and folding table. My question is the order to follow for assembly? I am thinking,
1 QCW Frame
2 Folding Table
3 Rails
Any thoughts?
Thanks
Brent
I would swap 1 & 2. Put together the folding table, assemble the QCW on top of it and then put the rails on. The QCW is heavier than it appears - easier to put the parts on individually vs lifting it assembled onto the table .
Ok got it, Thanks Jim
Qcw first, as the qcw is part of the table.
I assembled the QCW on the ground first. Then I assembled the rolling stand. Then just put the stand on top of the table
Yes, Thanks I have it assembled.